Home / Projects / Cornell NCRE Phase 2
Higher Education • Completed 2022

Cornell NCRE Phase 2

$272M+ Total
Ithaca, NY
Spring 2022 — 4 Months Early
1,200+ Student Beds
1,200+ bed expansion — LRS maintained a 5-month schedule lead throughout Phase 2.
$272M+
TOTAL PROJECT
1,200+
STUDENT BEDS
3
RESIDENCE HALLS
4 Mo Early
AHEAD OF DEADLINE
LEED Gold
SUSTAINABILITY
Project Gallery
[ MAIN PHOTO ]
[ PHOTO 2 ]
[ PHOTO 3 ]
[ PHOTO 4 ]
[ PHOTO 5 ]
Project Overview

Massive Campus Expansion

Cornell undertook the North Campus Residential Expansion to accommodate growing enrollment. The two-phase, 776,000 SF project included new residence halls, dining, and community spaces. Phase 2 constructed three residence halls providing 1,200+ beds, part of a $272M+ investment completed spring 2022 — four months early despite COVID challenges, supply chain issues, and workforce constraints.
LRS maintained a consistent 5-month lead throughout Phase 2, delivering precision site prep, utilities, grading, drainage, and stormwater management for this LEED Gold project.
Scope of Work

LRS Deliverables

As a trusted subcontractor to Welliver, LRS maintained a 5-month schedule lead throughout Phase 2 — ensuring seamless integration with the fast-tracked timeline on this massive campus expansion.
Site preparation and grading for residence hall foundations and surrounding areas
Utilities installation — storm drainage, electrical, catch basins
Comprehensive drainage systems and stormwater basin construction
Coordination with environmental controls and compliance requirements
Maintained 5-month lead ahead of schedule throughout the phase
Key Features

Project Highlights

3 Residence Halls

776,000 SF total

1,200+ Beds

Major enrollment expansion

LEED Gold

Sustainability certified

4 Months Early

Ahead of schedule

GC: Welliver

Trusted subcontractor

5-Month Lead

Consistently ahead of GC schedule
Technology & Approach

How We Deliver

GPS Machine Control

Precision grading across massive multi-building campus site

Fast-Track Coordination

Seamless integration with accelerated Welliver schedule

Environmental Controls

Full SWPPP compliance on sensitive campus environment

COVID Adaptation

Maintained schedule despite pandemic workforce and supply challenges
Impact & Results

Project Impact

Added modern housing for Cornell’s growing student population
Supported a LEED Gold-certified expansion focused on sustainability
Demonstrated reliability on large-scale institutional projects, finishing ahead of schedule
Contributed to Welliver’s success: Phase 2 turned over four months early
Start Your Project

Ready to Build with Confidence?

We’re selective — every client deserves our full attention.